includes the demolition of the existing is restroom and construction of a new restroom at washington square park. the project went into construction in june. and has been proceeding slowly since then. we're at approximately 75% complete and anticipate the project being completed next month and open to the public towards the end of the month. so you will probably see a report on that next month. but we did run into a few problems during construction, which resulted in change orders. we have provided you a list of change orders approved so far and pending. the majority of which we contribute to unforeseen conditions, the greatest item, which is about 14%, is associated with pg&e's direction to us to change the connection of power service to both the restroom and the park lighting. the project originally contemplated connecting to the power service at the existing location on filbert street, but for reasons unknown or unclear to me, pg&e directed us after the project started to connect on columbus street, which required the contractor to trench and install conduit around the children's playground a