also, we gave webcor, we gave them directions to start closing up some of the areas. we had 30 feet opened, and now that we know that it's 14 feet long, 7 feet wide, we're going to start putting that back in so we can gain some time on the back end so we don't have to wait and do the fix and then put it all back. and then, of course, the peer review, the verification, that's related to the brittle verification analysis. we brought on ruby and associations on december 17, and that's going to be ongoing working with the team and ruby associates getting to creating that list, and if any additional remediation has to be done, it'll be determined here, and we'll report on that on february , and then, the actual mitigation itself would happen at some point once we start getting data out of that review. so that's what's happened regarding the peer review panel. now, i will turn it over to ron to continue with what's going on on the rest of the facility. >> thank you, dennis, good morning, directors. i'm here to give the other half of this presentation, which is focused on fa