the subphase 2 b scope of work includes dpw project management oversee the subphase 2 b work. dpw has numerous gigzs divisions listed here along with pu c and mta and together they all provide support services to prepare and review the 100 percent construction documentation, bid documents, bid submittal and adenims and also conduct the contract negotiationism also the second amendment includes dpw's preparation and review of additional 95 percent construction documentation set, and dpw acceptance of granite pavers, benches, trash receptacles and rain gardens twhin within the project. the proposed second amendment amount for the contract in total is 383, 268. since the 2 a contract was approved by the commission, that was done in the first amendment which was brought to you last time. mta spent about $100 thousand than what was in that phase and so what we have done is we now included it within phase 2 b and this will be put towards the dpw work within the second amendment. so therefore the net cost for the second amendment is $283, 268 and 1, 1 12, 791. with that, oscar and my