and that will provide us at the plant with redundant power to southeast from petrero substation. that is approximately $14.5 million increase. north shore wet weather pump station has been delayed six months for refinement to the scope and that will result in a cost reduction of approximately $15 million. central bay assessment improvement project, we're delaying six months to complete addition geo tech work for the tunnel. we did have unforeseen electrical work and code khaungs and that was a project that has been awarded for construction that's an impact of $8.3 million. and five months. also some change on some of our flooding projects. we have a six-month increase due to engineering efforts to complete the engineering report. cayuga avenue storm weather detention has been extended due to extended coordination with cal trans. if we can bring the slides up. thank you. here we are. phase one of the program. these are all the projects that have been scoped based on the approved levels of service representing the $2.9 billion that we're starting with. and we are currently under wa