the contractor staging will move over in front of the jcc building. retaining public parking, on the california street garage, and that we will also have contractor staging, and likely contractor offices on the existing structure that is currently on the northwest portion of the project. this slide demonstrates when the masonic/euclid phase is complete. the center phase is still under construction. this shows the pedestrian access way, and also the vehicular access for the masonic and euclid building, under the masonic garage and euclid garage , while the buildings are under construction. it was still be pedestrian access, public parking, along california street in surface parking lot. also, contractor staging will be able to occur on the west portion of the site where there is existing parking. when plaza anb and walnut phase comments, the center, it is assumed to still be in progress. the contractor staging will take place at the west side of the center a and b buildings. while the entire california frontage is under construction. this is our access