approved the construction
contract for the san antonio
back up pipeline.
we now have 18 projects in
construction and only have five
remaining project in
pre-construction.
two of those are supporting
projects that do not contribute
to the los goals of the
program.
we essentially have only one
seismic project that i've yet
to enter construction.
so, we're definitely ramping
down here quickly.
now, following the largest cost
increase forecasted in the
program last quarter due to the
deferring site conditions at
cal var as, we are now
forecasting the overall cost of
the program to be slightly over
the approved budget of $4.6
billion.
specifically, our forecast is
now $17.6 million above the
currently approved budget.
and the projects that have the
largest forecasted cost
increases of course include the