the modular building, which is
the ac transit admin building
gets delivered here in a few
weeks.
it will take 6 to 7 weeks to
build it out.
it's our last item on the bus
storage facility.
that will be the keys for that
trailer.
it won't be done until june
25th and then we'll hand the
keys to them on june 26th
assuming all goes well with
the -- no gremlins in the
system.
also the concrete paving, this
picture was taken for the first
pictures of the concrete
pavement, which the entire area
between second and third gets
paved out.
the first one was a few weeks
ago.
they have over 50% of it out,
and i walked it on tuesday.
they are making good progress on
the concrete pavement out there.
an update on the bus on-ramp
merge, that has been -- we're at
a good spot in the process right
now thanks to the caltrans staff
specifically al lee have helped