cdsm, we will show you pictures of that as well. the west end of the project, everything west of first street is completely surrounded by shoring wall, at this point. zone 3, about two-thirds of the way down with the cdsm there. we will have all the shoring wall complete by the end of the week with the exception of street crossings, which rely on utility relocations. director ortiz: could you refresh my memory on the cdsm. >> cement deep shoring wall. we use that to create the perimeter around the project. zone 4. we continue to buttress work. that has made good progress. we are just over 2.5 shafts per week, which is the goal to get to to complete our work on project. this week, having to report we will complete three full shafts. on the screen now you can see we have completed the sea dsm -- cdsm on the west end of the project. we mobilized to the south side and will complete that were before the end of the month. east end of the project from freemont through beale street has been completed. all that will be left on the shore wall